Pine St Nambour · Council RFI Response

Action Tracker

15
To do
0
In progress
0
Blocked
0
Done
Phase 1 — Survey & Design
Unblocked, start now
RFI 1a
Engage surveyor — quote & commission detail survey
Jake
RFI 1b–g
Update site plan — fencing, retaining walls, materials & 3D views
TeknaSurvey
RFI 2
Rework front façade — balcony, eaves, articulation, materials
Tekna
RFI 4
Update floor plans — POS compliance & remove MPR room
Tekna
RFI 11
Update levels to flood search certificate
Tekna
RFI 15
Update plans — 10 bins on kerb at crossover
Tekna
Contract
Finalise pricing & execute build contract
TeknaPatrick & Rodger
Finalised plans
Phase 2 — Engineering
After architecture updated
RFI 5–6
Update crossover width (6.2m), power pole clearance & garage door (3.0m)
AuxiliumRFI 1–4
RFI 8
Retaining wall details — 150mm offset from boundary
AuxiliumSurvey
RFI 13
MRV space + 6.2m driveway + loading hardstand
AuxiliumRFI 1–4
Phase 3 — Neighbour Consent & Stormwater
Critical path item
RFI 9
Get neighbour consent — Lot 14 RP63950 easement letter
Jake
RFI 7
SWMP quality — MUSIC model or SC6.14.3 alternative
AuxiliumRFI 9
RFI 10
SWMP — Carter Rd capacity & peak flow calcs
AuxiliumRFI 9
RFI 12
External stormwater catchments, flows & drainage easement
AuxiliumRFI 9
Phase 4 — Landscape
Quote first, then engage
RFI 14
Landscape plan — 2m buffer, street trees, retaining/fence details
LandscapeRFI 1–4
High priority
Medium
Low